Takt Time, Cycle Time, and Production Capacity
Compare demand takt, capacity, loading, and required machine count for a single process using the measured cycle of identical machines.
Use the same period and product unit throughout. Required machine count is an estimate based on identical-machine capacity; production sequence, staffing, and material constraints are not checked.
Results
—min/good unit
—machines
- Good-unit capacity with current machines
- —units/period
- Good-unit capacity per machine
- —units/period
- Demand as a percentage of current capacity
- —%
- Additional machines needed
- —machines
- Good-unit shortfall against demand
- —units/period
- Completed attempts per machine
- —units/period
- Available running time per machine (after setup and downtime)
- —min/period
- Entered measured cycle time
- —min/attempted unit
Results update automatically when the required values are entered.
Method, applicability and sources
Calculation method
Required takt = available production time per machine ÷ good-unit demand for the same period (undefined for zero demand). Completed attempts per machine = ⌊(available time − setup time per machine) × uptime ÷ measured cycle⌋. Good-unit capacity per machine = ⌊completed attempts × good-unit rate⌋. Current capacity = per-machine capacity × parallel machines. Required machines = ⌈demand ÷ good-unit capacity per machine⌉ (undefined for positive demand with zero capacity). Load = demand ÷ current capacity × 100%. Deduct setup once from time; include loading/unloading only in the measured cycle, unplanned downtime only in uptime, and defects only in the good-unit rate.
Worked example (hypothetical values)
With 480 minutes per machine, demand of 240 good units, and a measured cycle of 3 min/unit, required takt is 2 min/good unit. Basic per-machine capacity is 160 units, requiring 2 machines. Load is 150% with 1 machine or 75% with 2.
Applicability and limitations
A single process with identical machines and cycle times operating independently in parallel, using consistent setup, uptime, and good-unit conditions per machine during the same period. Excludes mixed-product scheduling, process dependencies, staffing, material constraints, scheduling by setup count, duplicate application of OEE, probabilistic quality guarantees, and validation of a feasible production plan.
Method and sources
Method: B089 single-process capacity v1.0 (2026-11-13). Data recorded: 2026-11-13.