Compare energy, emissions and water use per unit of IT energy over a common period and facility boundary

Inclusive. Use actual data for 12 consecutive months.

Inclusive. For example, a January 1 start ends December 31.

All energy within the same boundary, including IT, cooling and power infrastructure. Include non-electric energy already converted to kWh.

Servers, storage, networking and other IT energy over the same 12 months and boundary. Zero cannot be used.

Enter category 1 in kgCO₂ and category 2 in kgCO₂e. This calculator does not aggregate emission sources or select factors.

Annual total consistent with the selected category. Do not enter 0 when unknown.

Annual withdrawals minus returned water within the data-center boundary. Keep reuse and flow boundaries consistent. Negative values are not clipped.

Results

Results update automatically when the required values are entered.

Method, applicability and sources

Calculation method

For the same facility boundary and 12 consecutive months: PUE = total facility energy (kWh) / IT energy (kWh); CUE = verified operational CO₂ or CO₂-equivalent emissions (kg) / IT energy (kWh); WUE = net water use (m³) ×1000 / IT energy (kWh). WUE in L/kWh is numerically equivalent to m³/MWh. Net water = withdrawals − returned water. Confirm numerator boundaries separately under the standard's measurement category.

Worked example (hypothetical values)

Hypothetical example: January 1–December 31, 2025; facility energy 1,800,000 kWh, IT energy 1,200,000 kWh, category 2 emissions 720,000 kgCO₂e, net water 1,800 m³. PUE =1.5; CUE =0.6 kgCO₂e/kWh; WUE =1.5 L/kWh.

Applicability and limitations

Twelve consecutive months of operational data for one data center or a facility whose usage can be metered separately from other uses. Does not impute missing measurements or allocations, select emission factors, convert generation/fuel/heating/cooling to kWh, classify WUE categories, certify measurement-category compliance, annualize short periods or simply average multiple facilities. Do not mix boundaries or periods.

Method and sources

Method: PUE: ISO/IEC 30134-2:2026 §5.1 / CUE: ISO/IEC 30134-8:2022 §§5 and 6.2.2 / WUE: ISO/IEC 30134-9:2022 §§5 and 6.2. Data recorded: 2026-11-13.