Search Tools

Convert rise, horizontal run, and slope for a straight ramp with a constant gradient, and calculate dimensions for an inline flight-and-landing layout.

Rise and horizontal run are calculated in the same cm unit. The flight layout is a dimensional estimate with inline landings and does not assess compliance with facility-specific standards.

What to calculate

Height difference between the ends. Enter the absolute value for either ascent or descent.

Horizontal projection, not distance along the sloping surface.

Optional for a flight layout; provide together with intermediate landing length. Statutory limits are not filled automatically.

Optional for a flight layout. Excludes level areas at the top and bottom.

Results

Results update automatically when the required values are entered.

Method, applicability and sources

Calculation method

Let H be rise (cm) and R the horizontal run of the sloping sections (cm). Slope (%) = 100H/R; N in 1:N = R/H; angle (°) = atan2(H,R) × 180/π; sloping length (cm) = hypot(H,R). For slope inputs, use H/R = p/100 for %, H/R = 1/N for 1:N, or H/R = tan(θ) for an angle. Flight layout: n = max(1, ceil(H/hmax)), with n − 1 intermediate landings and equal rise and run in each flight. Total horizontal run = R + (n − 1)L; travel-surface length = sloping length + (n − 1)L. H = 0 with R >0 is level; R = 0 is not treated as a ramp.

Worked example (hypothetical values)

For a rise of 50 cm and slope of 1:12, horizontal run = 50 × 12 = 600 cm (6 m), sloping length = √(600² + 50²) ≈6.0208 m, slope ≈8.3333%, and angle ≈4.7636°.

Applicability and limitations

Checking planned dimensions of general ramps. Users specify criteria applicable to the facility. Excludes automatic legal compliance checks, landing width and turning space, switchback layouts, actual site footprint, end clearances, handrails, ramp width, slope transitions, and construction tolerances.

Methods used

  • Straight constant-slope ramp conversion and equal flights separated by landings (Geometric calculation v1.0 (2026-11-13)): scope Assumes a straight horizontal projection, constant ramp slope, and level landings placed in line with travel; region JP

Method and sources

Method: Right-triangle geometry v1.0 (2026-11-13). Slope and landing terminology references Article 6 of Japan's Ministry of Land, Infrastructure, Transport and Tourism Ordinance No.114 (2006).. Data recorded: 2026-11-13.